Task Dependency System
mise uses a dependency graph to manage task execution order and parallelism. This ensures tasks run in the correct order while maximizing parallel execution.
Dependency Graph Resolution
When you run a task, mise builds a directed graph of the selected tasks and their declared dependencies, then rejects cycles. In this example, selecting deploy includes all of the prerequisites shown; arrows point from prerequisite to dependent:
This graph ensures that:
- Dependencies run before dependents
- Independent tasks run in parallel
- No circular dependencies exist
- Failed dependencies prevent dependents from running
Dependency Types
mise supports three types of task dependencies:
depends - Prerequisites
Tasks that must complete successfully before this task runs:
[tasks.test]
depends = ["lint", "build"]
run = "npm test"depends_post - Cleanup Tasks
Tasks that run after this task completes (whether it succeeded or failed):
[tasks.deploy]
depends = ["build", "test"]
depends_post = ["cleanup", "notify"]
run = "kubectl apply -f deployment.yaml"Regular dependencies of cleanup tasks belong to the same post-phase subtree and do not start until the parent task has completed. mise runs that subtree if the parent started, even when the parent fails, but skips the entire subtree when a regular dependency fails before the parent can start. A task used as both a regular dependency and a post-dependency is executed separately in each phase.
wait_for - Soft Dependencies
Tasks that must finish first if they are already scheduled. wait_for does not schedule them. A missing task definition still causes an error unless the reference sets optional = true; see wait_for.
[tasks.integration-test]
wait_for = ["start-services"] # Only waits if start-services is also being run
run = "npm run test:integration"Parallel Execution Engine
Job Control
mise executes tasks in parallel up to the configured job limit:
mise run --jobs 8 test # Use 8 parallel jobs
mise run -j 1 test # Force sequential executionThe default is 4 parallel jobs, but you can configure this globally:
# ~/.config/mise/config.toml
[settings]
jobs = 8Example Execution Flow
Given these tasks:
[tasks.lint]
run = "eslint src/"
[tasks.test-unit]
depends = ["lint"]
run = "npm run test:unit"
[tasks.test-integration]
depends = ["lint"]
run = "npm run test:integration"
[tasks.build]
depends = ["test-unit", "test-integration"]
run = "npm run build"Execution with --jobs 2:
Time →
0s: [lint]
5s: [test-unit] [test-integration] # Run in parallel after lint
15s: [build] # Waits for both testsTask Discovery and Resolution
Task Sources
mise loads inline TOML tasks, included task files, and executable file tasks from the active configuration hierarchy. A child configuration can override a parent configuration. An inline metadata-only definition can also add properties to an existing command or file task.
There is no single source-type ordering that describes every combination. See task_config.includes for include ordering, command replacement, and metadata overlays. Use mise tasks info <task> to inspect the selected definition.
Task Resolution Process
When you run mise run build, mise:
- Discovers all tasks from all configuration sources
- Resolves the task name (handles aliases and partial matches)
- Builds the dependency graph including all dependencies
- Validates the graph (checks for circular dependencies)
- Executes in dependency order with parallelism
Task Resolution Across Directories
Tasks from parent directories are available in subdirectories and can be overridden:
project/
├── mise.toml # defines: lint, test, build
└── frontend/
└── mise.toml # overrides: test, adds: bundleIn frontend/, you have access to lint (from parent), test (overridden), build (from parent), and bundle (local).
Advanced Dependency Features
Conditional Dependencies
Use task arguments for conditional behavior:
[tasks.test]
depends = ["build"]
run = '''
#!/usr/bin/env bash
if [ "$1" = "--with-lint" ]; then
mise run lint
fi
npm test
'''The shebang selects Bash, which must be installed on the host. Without it, mise uses the platform default inline shell (sh -c on Unix, cmd /c on Windows), so the bash [ ... ] test would fail to parse on a Windows host. For richer argument handling, prefer the usage field instead of positional parameters.
Dynamic Dependencies
A script can invoke another task conditionally. These nested invocations are separate runs; they are not added to the original dependency graph and do not appear in mise tasks deps:
#!/usr/bin/env bash
#MISE depends=["setup"]
# Additional conditional dependency
if [ ! -f ".env" ]; then
mise run generate-env
fi
npm startCross-Project Dependencies
Enable monorepo mode and declare the project roots before referencing their tasks. For projects named api and frontend:
[tasks.deploy-all]
depends = [
"//api:build",
"//frontend:build",
"deploy-infrastructure"
]
run = "echo 'All services deployed'"Performance Optimizations
Source and Output Tracking
Tasks can skip execution if sources haven't changed:
[tasks.build]
sources = ["src/**/*.ts", "package.json"]
outputs = ["dist/**/*"]
run = "npm run build"mise only runs the task if:
- Source files are newer than output files
- The task has never been run
- Dependencies have changed
Incremental Execution
Use mise run --force to ignore source/output checking:
mise run --force build # Always run, ignore source changesParallel File Watching
Use mise watch for continuous development:
mise watch # Watch the default task
mise watch build test # Watch specific tasksThis automatically reruns tasks when their source files change.
Debugging Task Dependencies
Visualize Dependencies
mise tasks deps build # Show build's declared dependencies
mise tasks deps --dot > deps.dot # Generate graphviz diagramExecution Tracing
mise run --verbose build # Show task execution details
mise run --dry-run build # Show what would run without executingCommon Issues
Circular Dependencies:
Error: Circular dependency detected: test → build → testSolution: Remove the cycle or split the shared work into a separate prerequisite. wait_for also creates ordering constraints when both tasks are scheduled, so it is not a general way to break a cycle.
Missing Dependencies:
Error: Task 'build' depends on 'lint' but 'lint' was not foundSolution: Define the missing task or remove the dependency.
Slow Parallel Execution:
- Check if tasks have unnecessary dependencies
- Use
mise tasks depsto verify the declared dependency graph (depends,wait_for,depends_post) - Consider increasing
--jobsif you have spare CPU cores